December Update

Updated: Aug 14, 2023

Highlights so far:

  • Interior demolition work is done.

  • Old pavement from parking lot and drive-through removed north of the building

  • Storefront window openings are being cut and framed in on the north side.

  • New windows on the south side are cut in.

  • Some minor framing work inside has begun.

  • We anticipate removing a portion of the interior wall between the north 1/3 and middle 1/3 to open the space up in the next month.